Nearly nine years after construction began, Bangladesh's first nuclear power is reaching homes and factories. Unit 1 of the Rooppur Nuclear Power Plant in Pabna was synchronised with the national grid on a trial basis at 3:16 PM on Tuesday, November 17. It first supplied up to 350 MW, then was eased back to 300 MW to keep the grid stable.
Science and Technology Minister Fakir Mahbub Anam, who was present, called it a historic achievement. The power board said the grid stayed stable.
This is not yet commercial operation. The first connection lasts 8 to 10 hours, followed by testing and short reconnections. The minister hopes the unit reaches its full 1,200 MW in late January or early February 2027. The contract requires 10 months of trial running before permanent supply.
The project cost has risen to Tk 1.39 lakh crore, and the second unit is still being built. For Munshiganj's factories and cold storages, steady new power on the grid could be welcome news.